The GPU Cluster Acceptance Test You Skipped

How to acceptance-test a new GPU cluster layer by layer, grade nodes against the fleet, and tie the results to the contract before you sign off.

Topics: HPC & Power, MLOps

Your new GPU cluster arrives. The vendor’s checklist says every node passed, and nvidia-smi shows eight GPUs per box. Two weeks into your first large training run, step times start to wander and nobody can say why. The cause is usually mundane: one GPU throttling, one cable running degraded, one storage target that chokes during checkpoints. Acceptance testing is when you find those faults. It’s also the last point where fixing them is clearly the vendor’s job instead of yours.

Why “it powers on” isn’t acceptance

Synchronous data-parallel training runs at the speed of its slowest rank. Every all-reduce waits for the last GPU to report. One degraded component slows the whole job, not just one node.

Most hardware faults don’t fail outright. They degrade:

  • A GPU passes a short check, then throttles after it heat-soaks under sustained load.
  • An InfiniBand or RoCE link trains at a lower speed than it should, or piles up symbol errors and retransmits.
  • A PCIe slot negotiates a narrower link or an older generation than the card supports.
  • GPU memory corrects ECC errors quietly until it starts remapping rows or logging Xid errors.

Vendor burn-in tends to be per node and short. Your workload is multi-node, long and sustained. Test for the workload you’ll actually run.

A layered test plan

Layer Tools What it catches
GPU and node dcgmi diag -r 3, nvidia-smi -q, lspci -vv Faulty GPUs, ECC and row-remap issues, wrong PCIe width or generation, power and thermal throttling
Fabric perftest (ib_write_bw, ib_read_lat), nccl-tests, ibdiagnet Slow or flapping links, miscabling, bad switch ports, topology mistakes
Storage fio, a real checkpoint write and restore Metadata bottlenecks, slow targets, dataloader starvation
Sustained load Your own training job, or HPL, for days Intermittent faults, heat soak, problems that only show up over time

GPU and node

Run DCGM diagnostics on every node, not a sample. Compare each GPU’s and NIC’s negotiated PCIe link (LnkSta) against its capability (LnkCap). Check the row-remapping and retired-page status in nvidia-smi -q, and grep kernel logs for Xid events after each test.

Fabric

Testing every node pair grows quadratically, so on larger clusters test each node against a known-good reference node, then within and across leaf switches. Then scale collectives up in steps: one node, two, four, half the cluster, all of it. If bus bandwidth drops sharply when a particular node joins, you’ve found your suspect.

# nccl-tests built with MPI support; one task per GPU, 8 bytes to 8 GB
srun -N 16 --ntasks-per-node=8 --gpus-per-node=8 \
  ./build/all_reduce_perf -b 8 -e 8G -f 2 -g 1

After the run, pull port error counters from the switches. A link that passed the bandwidth test while logging errors will fail later.

Storage

Write a checkpoint the size your largest job will produce, from all nodes at once, and time it. Then restore it. Separately, run your dataloader alone at the throughput your training step needs. Storage that benchmarks well under fio can still collapse under thousands of small-file reads.

Sustained load

Run for days, not hours. Your own training job is the best test because it exercises compute, fabric and storage together. Log per-step time and look for slow outlier steps, not just the average.

Grade against the fleet, not the datasheet

Spec-sheet peaks are measured under ideal conditions, and arguing over them gets you nowhere. Your own fleet is a better reference. Identical nodes should produce tightly clustered results, so collect per-node numbers for GEMM throughput, NCCL bus bandwidth, storage throughput and sustained clocks, then flag anything well below the median.

Drain outliers so the scheduler stops placing work on them while they’re investigated:

scontrol update nodename=gpu-017 state=drain reason="low nccl busbw"

Save the full result set as your baseline. Rerun it after driver or firmware updates and after any RMA. Without a baseline, every later slowdown turns into a debate. This is the same trap as the staging environment that lies to you: a check that passes in conditions unlike production tells you little.

Write it into the contract before delivery

Acceptance criteria agreed after the hardware lands are weak. Settle these in writing before anything ships:

  • Tests, scale and duration. Which tools, at what node counts, and for how long.
  • Pass criteria. Include fleet-relative criteria (no node below an agreed fraction of the median), not just “completes without error.”
  • Remediation. How long the vendor has to fix failures, and a requirement to retest replaced parts and the nodes around them.
  • Payment linkage. Tie final acceptance or a payment milestone to passing.
  • Evidence. Who runs the tests, who can see the raw logs, and how long they’re kept.

This is engineering guidance. Have procurement and counsel turn it into contract language.

Rented and reserved cloud clusters need this too. Billing usually starts at handover, so test on day one and document what you find. That record is your basis for asking for replacement nodes or credits. Secondhand hardware needs even more scrutiny, as covered in the A100 surplus hiding in plain sight.

If you’re sizing or buying a cluster and want the acceptance plan built in from the start, begin with the Compute & Power Plan.